The Exin PRINCE2 Foundation certification is an internationally-recognized validation that identifies persons who earn it as possessing skilled in Exin Project Management Certification. If a candidate wants significant improvement in career growth needs enhanced knowledge, skills, and talents. The Exin PRINCE2 Foundation PR2F Exam certification provides proof of this advanced knowledge and skill. If a candidate has knowledge of associated technologies and skills that are required to pass the Exin PRINCE2 Foundation PR2F Exam then he should take this exam.
NEW QUESTION 168
Which is an objective of the 'starting up a project' process?
- A. To define the project quality management approach
- B. To approve the initiation stage
- C. To select the project mandate
- D. To appoint the project management team
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Starting_Up_a_Project#Purpose
NEW QUESTION 169
Which is an objective of the 'directing a project' process?
- A. To define how risks, issues and changes will be managed
- B. To obtain approval for completed products
- C. To ensure corporate or programme management has an interface to the project
- D. To review and approve a project mandate
Answer: C
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Directing_a_Project#Objective
NEW QUESTION 170
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
- A. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
- B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
- C. Create user and supplier groups
- D. Create a separate Project Board to manage the supplier elements of the project
Answer: C
NEW QUESTION 171
Which is a responsibility of the managing level within the project management team?
- A. Appoint the project management team
- B. Set project tolerances
- C. Approve stage completion
- D. Ensure that the products are produced within the constraints agreed with the Project Board
Answer: D
NEW QUESTION 172
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
- A. Team Plan
- B. Work Package
- C. Product Description
- D. Stage Plan
Answer: B
NEW QUESTION 173
Which is a factor when deciding the duration of a management stage?
- A. The level of risk in the project
- B. The cost of the stage
- C. The number of products to be produced in the project
- D. The work packages to be delivered
Answer: A
Explanation:
Explanation
Reference https://www.prince2primer.com/the-design-of-prince2-management-stages/
NEW QUESTION 174
What product is used to maintain a record of those who have an interest in the project and their information requirements?
- A. Project Plan
- B. Communication Management Strategy
- C. Project Brief
- D. Project Product Description
Answer: B
NEW QUESTION 175
Which enables the project's products and all interdependencies to be clearly identified and documented?
- A. Quality review technique
- B. Quality Management Strategy
- C. Product breakdown structure
- D. Product-based planning technique
Answer: D
NEW QUESTION 176
Which is a task of product-based planning?
- A. Design the plan
- B. Prepare the schedule
- C. Analyze the risks
- D. Create the product flow diagram
Answer: D
NEW QUESTION 177
Which product is used by the Project Manager to authorize work?
- A. Team Plan
- B. Work Package
- C. Product Description
- D. Stage Plan
Answer: B
NEW QUESTION 178
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
- A. the project board has agreed the project strategies
- B. the 'starting up a project' process is completed
- C. corporate, programme management or the customer have authorized a project
- D. the project mandate has been approved by the project board
Answer: B
Explanation:
Explanation
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp
NEW QUESTION 179
Which of the following statements about the Project Initiation Documentation are true?
1.The Project Initiation Documentation is used to ensure that a sound basis exists.
2.The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,
- A. Neither 1 or 2 are true
- B. Only 1 is true
- C. Only 2 is true
- D. Both 1 and 2 are true
Answer: D
NEW QUESTION 180
According to the 'continued business justification' principle, what must project benefits be aligned to?
- A. The technology available
- B. The direction of the project board
- C. The business objectives
- D. Regular deliveries throughout the project
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-principle-continued-business-justification.php
NEW QUESTION 181
What is an off-specification?
- A. A major risk
- B. A new requirement
- C. A type of issue
- D. A quality tolerance
Answer: C
NEW QUESTION 182
Which activity takes place within the Managing a Stage Boundary process?
- A. Produce Highlight Reports
- B. Authorize a Stage Plan for the next stage
- C. Produce an Exception Plan
- D. Take corrective action within the limits of a stage's tolerance
Answer: C
NEW QUESTION 183
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
- A. Neither 1 or 2 are true
- B. Only 1 is true
- C. Only 2 is true
- D. Both 1 and 2 are true
Answer: D
Explanation:
Section: Volume A
NEW QUESTION 184
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
- A. define a coding system to provide a unique identifier for the products within
- B. summarize the results of the quality activities performed on
- C. provide a framework to design, develop and maintain
- D. define the project benefits to be achieved by each of
Answer: C
Explanation:
Section: Volume B
Explanation
NEW QUESTION 185
From whom does a Team Manager obtain approval for a completed product?
- A. Senior Supplier
- B. Project Manager
- C. The authoritydefined in the Product Description
- D. Project Support
Answer: C
NEW QUESTION 186
Which is an objective of the Closing a Project process?
- A. Prepare the plan for the next stage
- B. Check that all benefits are realized before closing a project
- C. Produce a Benefits Review Plan to identify what benefits are expected
- D. Assess any benefits that have already been realized
Answer: D
NEW QUESTION 187
......
Who should take the PRINCE2-Foundation: PRINCE2 Foundation Exam
PRINCE2 is one of a structured technique of project management and certification program for practitioners. It highlights the division of tasks into controlled and achievable steps. It is intended for project managers, project managers and all project managers. This quality. This quality. This comprises project committee members (e.g. SCO), the team leaders (e.g. Product delivery managers) and the project assurance (e.g. Business Change Analysts), project support (e.g. project and program office employees) and operational line managers/staff. This also applies to other key staff involved in the idea, development and execution of projects. In addition to investing in personal growth and broader training via a real-life project experience, it is essential to guarantee that you do this. As you know, certification plays a key role in your economical, personal and other development. You have to know how you use HR so the odds of choosing your candidate are very high and so you may obtain a prestigious position in your business. In addition, when candidates are certified, the business has trust in the execution of projects.
PRINCE2Foundation Study Guide Brilliant PRINCE2Foundation Exam Dumps PDF: https://www.dumpsvalid.com/PRINCE2Foundation-still-valid-exam.html
View PRINCE2Foundation Exam Question Dumps With Latest Demo: https://drive.google.com/open?id=16RvLrvNBHJtZGJklIhYRUYnrt8GSRJTV