PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:

TopicDetails
Topic 1
  • Understand the focus areas in an agile contex
  • Understand key concepts relating to PRINCE2
Topic 2
  • Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
Topic 3
  • Understand key concepts relating to projects and PRINCE2 Agile
Topic 4
  • Understand the agile ways of working, key terms and techniques

 

NEW QUESTION 27
Which role is responsible for facilitating the Agilometer assessment?

  • A. Team manager
  • B. Customer subject matter expert
  • C. Project manager
  • D. Project board

Answer: C

 

NEW QUESTION 28
Which statement explains the PRINCE2 Agile behavior of 'exploration'?

  • A. It seeks out feedback collaboratively from project stakeholders
  • B. It displays the progress rate to everyone using burn-down charts
  • C. It uses the most effective channel to communicate information
  • D. It empowers the project management team at the delivery level

Answer: A

 

NEW QUESTION 29
Which is a key objective of running a workshop?

  • A. To encourage collaboration and create the defined outputs from the event
  • B. To make day-to-day decisions on behalf of the delivery team within a sprint
  • C. To make daily progress visible to the delivery team and key stakeholders
  • D. To communicate decisions to the wider stakeholder community

Answer: A

 

NEW QUESTION 30
What is the definition of a timebox?

  • A. A regular event that looks at how processes can be improved
  • B. A description of the rate of progress a team is making
  • C. A tool to write a requirement in the form of who, what and why
  • D. A period where work is carried out to achieve a goal

Answer: D

 

NEW QUESTION 31
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

  • A. Typical
  • B. Preferable
  • C. Effective

Answer: C

 

NEW QUESTION 32
Which is a purpose of the quality theme?

  • A. To define the specific conditions that enable a product to be usable
  • B. To assess any potential improvements to a product
  • C. To evaluate whether the project continues to be achievable
  • D. To determine how the means of delivering products is communicated

Answer: C

 

NEW QUESTION 33
What needs to happen when new detailed requirements are added to a timebox?

  • A. The delivery milestones should be reviewed and re-planned
  • B. More people should be added to the delivery team
  • C. Formal change control should be applied
  • D. Requirements of a similar level of effort should be removed

Answer: D

 

NEW QUESTION 34
During which process should release planning be done for the FIRST time?

  • A. Controlling a stage
  • B. Initiating a project
  • C. Managing product delivery
  • D. Managing a stage boundary

Answer: D

 

NEW QUESTION 35
Which statement about the 'accept that the customer doesn't need everything' target is correct?

  • A. It can result in the early delivery of a minimum viable product
  • B. It allows misunderstandings to be dealt with appropriately
  • C. It is achieved by managing the culture of the team carefully
  • D. It gives confidence on the progress of the project

Answer: B

 

NEW QUESTION 36
Which statement explains how the 'learn from experience' principle is applied in an agile context?

  • A. It provides guidance on mapping PRINCE2 roles to an agile environment
  • B. It focuses on the prioritization and decomposition of requirements
  • C. It is supported by the 'inspect and adapt' concept
  • D. It integrates releases within management stages

Answer: C

 

NEW QUESTION 37
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks

  • A. 1 and 2
  • B. 1 and 4
  • C. 2 and 3
  • D. 3 and 4

Answer: D

Explanation:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help

 

NEW QUESTION 38
What should the business case state about the minimum viable product (MVP)?

  • A. That the MVP is the same as project viability
  • B. That the MVP must go into operational use
  • C. When the MVP will be defined
  • D. What the MVP is

Answer: B

 

NEW QUESTION 39
Which process can take place during a release review workshop?

  • A. Managing a stage boundary
  • B. Controlling a stage
  • C. Managing product delivery
  • D. Directing a project

Answer: C

 

NEW QUESTION 40
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By allowing a lot of detail at the start
  • B. By requiring details at the start
  • C. By avoiding too much detail at the start
  • D. By preventing the analysis of details at the start

Answer: D

 

NEW QUESTION 41
To help with prioritization, what is MOST important when understanding the difference between scope and quality?

  • A. Defining non-functional requirements before functional requirements
  • B. Creating non-functional requirements with user stories
  • C. Combining functional and non-functional requirements
  • D. Differentiating functional from non-functional requirements

Answer: D

 

NEW QUESTION 42
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by allowing enough time for testing
  • B. It delivers the early realization of benefits
  • C. It is achieved by using the same team members
  • D. It gives confidence on the progress of the project

Answer: B

Explanation:
Reference:
%20level%20is%20met

 

NEW QUESTION 43
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

  • A. To fail fast, if you are going to fail
  • B. To use empiricism, based on knowledge that comes from experience
  • C. To build, measure, learn from your experiences
  • D. To create a minimum viable product to manage uncertainty

Answer: B

 

NEW QUESTION 44
Which statement about the waterfall methodology definition is CORRECT?

  • A. It is a behavior that involves making things transparent
  • B. It promotes the use of experiments carried out in a scientific way
  • C. It has distinct goals for each stage of development
  • D. It states that deadlines should not be moved

Answer: C

 

NEW QUESTION 45
Which statement about velocity is CORRECT?

  • A. It is shown by the ideal line on a bum-down chart
  • B. It describes how much work is getting done
  • C. It is based on the concept of rationalism
  • D. It tracks the time and cost of a timebox

Answer: B

 

NEW QUESTION 46
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance is flexed
  • B. Cost tolerance can be fixed or flexed
  • C. Cost tolerance can be fixed and flexed
  • D. Cost tolerance is fixed

Answer: A

 

NEW QUESTION 47
......

Latest PRINCE2-Agile-Foundation Exam Dumps - Valid and Updated Dumps: https://www.dumpsvalid.com/PRINCE2-Agile-Foundation-still-valid-exam.html

Verified PRINCE2-Agile-Foundation Exam Questions Certain Success: https://drive.google.com/open?id=1ojzf0f5ZODctzPwUuMoGL3tojyOMyCLp