AACE International AACE-PSP (Planning & Scheduling Professional) Certification Exam is a rigorous examination designed to test the knowledge and competency of professionals in the field of project planning and scheduling. AACE International is a renowned professional association for project management professionals, and their PSP certification program is recognized globally as a mark of excellence in the planning and scheduling profession.
NEW QUESTION # 44
The work breakdown structure is used to organize
- A. The smallest defined work packet
- B. "Smart activity ID codes" representing similar items of scheduled work
- C. Similar activity coding of schedule activities
- D. The chart of accounts
Answer: A
NEW QUESTION # 45
When resource leveling craft labor for a critical path schedule, the scheduler
- A. Need only consider the non-union crafts persons.
- B. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
- C. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
- D. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
Answer: D
NEW QUESTION # 46
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 22 months.
- B. 20 months.
- C. 19 months.
- D. 21 months.
Answer: B
NEW QUESTION # 47
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?
- A. Cannot be determined.
- B. 12.
- C. 13.
- D. 14.
Answer: B
NEW QUESTION # 48
Project schedules help control all of the following EXCEPT for_____________________.
- A. Time
- B. Resources
- C. Cost
- D. Quality
Answer: D
NEW QUESTION # 49
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
- A. The correct recording of actual start dates.
- B. Estimating remaining durations of activities.
- C. Making "downstream" logic revisions as required.
- D. Entering the time impacts of delays and change orders.
Answer: C
NEW QUESTION # 50
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 2004.
- B. 2003 and 7001.
- C. 4001 and 5001.
- D. 4001, 5001 and 6001.
Answer: C
NEW QUESTION # 51
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
- A. 12-17-03 and 4 days of float
- B. 12-27-03 and 24 days of float
- C. 12-18-03 and 25 days of float
- D. 12-18-03 and 4 days of float
Answer: A
NEW QUESTION # 52
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
- A. B.
- B. W.
- C. S.
- D. C.
Answer: C
NEW QUESTION # 53
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 15 days.
- B. 10 days.
- C. 5 days.
- D. 0 days.
Answer: D
NEW QUESTION # 54
Is activity 7001 pictured correctly in the precedence diagram?
- A. No, the start-to-start and finish-to-finish relationships are backwards.
- B. No, the total float is not shown correctly.
- C. Yes, the duration is 48 days.
- D. Yes, except the early finish date is not shown.
Answer: C
NEW QUESTION # 55
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 18 work days
- B. 15 workdays
- C. 8 work days
- D. 7 work days
Answer: C
NEW QUESTION # 56
Resource planning must take all of the following into account except for
- A. Types of materials, equipment and labor skills required to complete the project.
- B. Earned value techniques established for the project.
- C. Time available to complete the project.
- D. Cash flow (expenditure) limitations for completing work on the project.
Answer: B
NEW QUESTION # 57
Total float is defined as the amount of time an activity can be delayed without impacting
- A. The buoyancy of a successor activity
- B. The end of that activity
- C. The next activity
- D. The overall project completion
Answer: D
NEW QUESTION # 58
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Preferential logic.
- B. Multiple calendars.
- C. Front end loading.
- D. Start and finish constraints.
Answer: C
NEW QUESTION # 59
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 15 days.
- B. 0 days.
- C. 10 days.
- D. 5 days.
Answer: D
NEW QUESTION # 60
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
- A. 2.3% (1 : 43.501).
- B. 3.9% (1 : 25.708)
- C. 8.6% (1 : 11.591)
- D. 9.1% (1 : 11.000).
Answer: A
NEW QUESTION # 61
......