Real C-ACT-2403 are Uploaded by DumpsValid provide 2026 Latest C-ACT-2403 Practice Tests Dumps.
All C-ACT-2403 Dumps and SAP Certified Associate - Project Manager - SAP Activate Training Courses Help candidates to study and pass the SAP Certified Associate - Project Manager - SAP Activate Exams hassle-free!
SAP C-ACT-2403 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
NEW QUESTION # 33
You are implementing SAP S/4HANA Cloud, public edition for your customer.How are your customer systems activated?
- A. Via the SAP Contact Center
- B. Via the SAP Cloud ALM
- C. Via the SAP Business Technology Platform
- D. Via the Central Business Configuration System
Answer: D
Explanation:
* C is correct because the Central Business Configuration System (CBC) is a tool that enables customers to activate their SAP S/4HANA Cloud, public edition systems by following guided steps and entering configuration data. Verified References:
* : Central Business Configuration Overview
NEW QUESTION # 34
Which functionality is available in Focused Build?
- A. Custom Code Management
- B. Test Management
- C. User Experience Monitoring
- D. Integration Monitoring
Answer: B
Explanation:
* B is correct because Focused Build provides a test management feature that supports the planning, execution, and reporting of test activities in SAP projects. It allows the creation and assignment of test cases, test packages, and test plans, as well as the tracking and monitoring of test results and defects.
Verified References:
* : Focused Build for SAP Solution Manager
NEW QUESTION # 35
When doing a new implementation on premise or private cloud, which system is recommended to demonstrate standard functionality in the Explore phase?
- A. Sandbox
- B. Starter
- C. Development
- D. Trial
Answer: A
Explanation:
A Sandbox system is recommended in the Explore phase to demonstrate standard SAP functionality and conduct initial testing. This environment allows for configuration and testing without affecting the live environment, helping the project team understand standard capabilities.
NEW QUESTION # 36
Which of the following tools facilitate secure communication between SAP cloud solutions and protected on-premise networks that CANNOT be accessed directly from the Internet?
- A. Cloud Integration Automation service
- B. SAP Build Cade
- C. Identity Authentication service
- D. SAP BTP Connectivity service
Answer: D
Explanation:
The SAP BTP Connectivity service facilitates secure connections between SAP cloud solutions and on-premise networks that are isolated from direct internet access, ensuring data security and compliance.
NEW QUESTION # 37
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
- A. Realize phase scope, planning, and budget should be completed and final.
- B. Release plan and sprint ceremony guidelines should be finalized.
- C. Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
- D. User stories on product backlog should be in ready state for the first 2 to 3 sprints.
Answer: C
Explanation:
* C is correct because in an Agile approach, the planning is done iteratively and incrementally, so the minimum requirement at the beginning of the Realize phase is to have sprint planning and sprint durations defined for the first 2 to 3 sprints. Verified References:
* : SAP Activate Project Management Certification Guide, page 117
NEW QUESTION # 38
What is the purpose of the scrum board?
- A. To visualize the resource load
- B. To show readiness of the release
- C. To visualize team progress
- D. To document the results of the fit-to-standard workshop
Answer: C
Explanation:
The scrum board is used to visually track team progress on sprint tasks. By displaying each task's current status, it provides transparency, helping team members and stakeholders stay updated on the sprint's progress.
NEW QUESTION # 39
What does the Side-by-Side extensibility option mean?
- A. Extending SAP S/4HANA using SAP ABAP Development Workbench.
- B. Extend SAP S/4HANA using APIs published on SAP Business Accelerator Hub.
- C. There are two SAP S/4HANA instances: one for standard code and another for custom developments.
- D. SAP S/4HANA extensions are context-aware and focused on tight integration.
Answer: B
Explanation:
Side-by-Side extensibility allows SAP S/4HANA to be extended using APIs and services available on SAP Business Accelerator Hub. This approach decouples customizations from the core system, enhancing flexibility and reducing the impact of updates.
NEW QUESTION # 40
What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Custom code is developed in System Conversion and adjusted in New Implementation of SAP u S/4HANA in the Realize phase. 4
- B. Custom code is adjusted in System Conversion and developed in New Implementation of SAP V U S/4HANA in the Realize phase.
- C. Data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase.
- D. Data is migrated in System Conversion and converted in New Implementation of SAP S/4HANA in the Realize phase.
Answer: B,C
Explanation:
* A is correct because custom code is adjusted in System Conversion and developed in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing custom code needs to be adapted to run on SAP S/4HANA. In New Implementation, new custom code needs to be developed to meet the customer's specific requirements.
* D is correct because data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing data needs to be converted to the new data structures and formats of SAP S/4HANA. In New Implementation, new data needs to be migrated from the legacy system or other sources to SAP S/4HANA. Verified References:
* : SAP Activate Project Management Certification Guide, page 127
NEW QUESTION # 41
Which of the following are capabilities of SAP Landscape Transformation Tool used in Selective Data Transition scenarios? Note: There are 3 correct answers to this question.
- A. Consolidation of systems
- B. Full set of historical transactional data
- C. Migration of selected applications
- D. Configuration of open backlog items
- E. Migration of business units
Answer: A,C,E
Explanation:
The SAP Landscape Transformation Tool enables selective migration by allowing the migration of specific applications and business units, as well as the consolidation of systems. It provides flexibility in data transition for selective data migration scenarios.
NEW QUESTION # 42
Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package? Note: There are 2 correct answers to this question.
- A. Business Process Scenarios
- B. Configuration Guides
- C. Building Blocks
- D. Scope Items
Answer: C,D
Explanation:
In SAP Best Practices for SAP S/4HANA Solution Packages, Scope Items and Building Blocks represent structured components. Scope Items define functional aspects, while Building Blocks provide detailed configuration steps.
NEW QUESTION # 43
Which of the following are SAP Activate workstreams?Note: There are 2 correct answers to this question.
- A. Data Migration
- B. Change Management
- C. Extensibility
- D. Project Management
Answer: A,D
Explanation:
* B is correct because Project Management is one of the SAP Activate workstreams. The Project Management workstream covers all the activities related to planning, executing, monitoring, controlling, and closing the project. It includes tasks such as defining project scope, schedule, budget, resources, risks, issues, quality, communication, and stakeholder management.
* D is correct because Data Migration is one of the SAP Activate workstreams. The Data Migration workstream covers all the activities related to preparing, extracting, transforming, validating, and loading data from legacy systems to SAP systems. It includes tasks such as defining data migration strategy, scope, approach, tools, roles, responsibilities, quality criteria, and testing scenarios. Verified References:
* : SAP Activate Methodology Workstreams Names update
* : SAP Activate Testing Workstream
NEW QUESTION # 44
Which steps should you perform while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project? Note: There are 2 correct answers to this question.
- A. Review Cutover Plan accelerator in the Data Management workstream.
- B. Review SAP S/4HANA Cloud best practices availability for your country.
- C. Review all the necessary Implementation Design Principles (IDPs).
- D. Review all the necessary leading practice process diagrams.
Answer: C,D
Explanation:
For a fit-to-standard analysis in SAP Data Warehouse Cloud, reviewing the necessary Implementation Design Principles (IDPs) and leading practice process diagrams ensures that the design aligns with best practices and project objectives.
NEW QUESTION # 45
Which of the following characteristics relate to the Focused Build for SAP Solution Manager Functionality? Note: There are 2 correct answers to this question.
- A. SAP delivers all knowledge required with the solution.
- B. SAP delivers all configuration values within your project.
- C. SAP delivers a standard solution with its own separate license.
- D. SAP delivers a standard solution without any additional coding required.
Answer: A,D
Explanation:
Focused Build for SAP Solution Manager is a standardized solution, provided by SAP with all necessary knowledge resources, requiring no additional coding for implementation. This functionality supports efficient project tracking and delivery.
NEW QUESTION # 46
Which of the following Accelerators can you find in the SAP Best Practices Explorer?Note: There are 2 correct answers to this question
- A. Test Strategy
- B. Stakeholder Identification Guide
- C. Process Diagram
- D. Test Case
Answer: C,D
Explanation:
* C is correct because Process Diagram is one of the accelerators that you can find in the SAP Best Practices Explorer. A Process Diagram is a graphical representation of a business process that shows the sequence of activities, roles, and systems involved in executing the process.
* D is correct because Test Case is one of the accelerators that you can find in the SAP Best Practices Explorer. A Test Case is a document that describes a scenario that needs to be tested, along with the expected results and test steps.
NEW QUESTION # 47
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path?
- A. Solution Validation and Delta Design
- B. Setup and Enablement
- C. Fit-to-standard
- D. Simplification and Custom Code Impact Analysis
Answer: C
Explanation:
* B is correct because Fit-to-standard is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path. Fit-to-standard is a process where the customer validates the fit of their business processes to the standard SAP S/4HANA Cloud solution and identifies any gaps or extensions that need to be addressed. Fit-to-standard is performed using a series of workshops where the customer reviews the best practice processes and scenarios provided by SAP and compares them with their own requirements. Verified References:
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 18
* : SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation
NEW QUESTION # 48
What can you find in the SAP Fiori apps reference library? Note: There are 3 correct answers to this question.
- A. Installation and configuration requirements for selected apps
- B. Shortcut to the Maintenance Planner tool to establish the technical update path
- C. Related app recommendations based on your usage profile
- D. Related app-specific SAP Fiori design guidelines
- E. Shortcut to the Quicksizer tool to estimate hardware requirements
Answer: A,C,D
Explanation:
* B is correct because installation and configuration requirements for selected apps are one of the things that you can find in the SAP Fiori apps reference library. The SAP Fiori apps reference library provides information on how to install and configure each app, such as required software components, backend configuration steps, and frontend configuration steps.
* C is correct because related app-specific SAP Fiori design guidelines are one of the things that you can find in the SAP Fiori apps reference library. The SAP Fiori apps reference library provides links to the app-specific design guidelines that describe the user interface and interaction patterns of each app, such as layout, navigation, controls, and dialogs.
* E is correct because related app recommendations based on your usage profile are one of the things that you can find in the SAP Fiori apps reference library. The SAP Fiori apps reference library provides suggestions on other apps that might be relevant or useful for you based on your role, industry, or business area.
NEW QUESTION # 49
What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.
- A. Analyze the functional and technical dependencies between user stories.
- B. Prioritize backlog user stories by business priority.
- C. Define objectives for each release.
- D. Estimate the backlog user stories.
Answer: B,C
Explanation:
The product owner's responsibilities include defining objectives for each release to align with business goals and prioritizing backlog items by business priority to ensure high-value deliverables are completed first. While the team estimates user stories, the product owner ensures clarity and prioritization.
NEW QUESTION # 50
Which functionality is available in Focused Build?
- A. Custom Code Management
- B. Test Management
- C. User Experience Monitoring
- D. Integration Monitoring
Answer: B
Explanation:
Focused Build for SAP Solution Manager includes comprehensive Test Management functionality. It enables users to manage test cases, execute test plans, and track testing results, which are essential for large-scale SAP projects.
NEW QUESTION # 51
Which systems are part of the private cloud edition landscape? Note: There are 2 correct answers to this question.
- A. Sandbox
- B. Starter
- C. Evaluation
- D. Production
Answer: A,D
Explanation:
In the SAP S/4HANA private cloud edition, Sandbox and Production systems are part of the landscape, providing environments for testing and productive operations, respectively. These systems support the full lifecycle of deployment and ongoing maintenance.
NEW QUESTION # 52
......
Valid Way To Pass SAP's C-ACT-2403 Exam with : https://www.dumpsvalid.com/C-ACT-2403-still-valid-exam.html
Free Test Engine For SAP Certified Associate - Project Manager - SAP Activate Certification Exams: https://drive.google.com/open?id=1kOM-eAcGXzXNUNo_piQSdbtW3aBqN1sN